Warning: Attempt to read property "post_parent" on null in /home1/nrusson/public_html/quotulatiousness.ca/blog/wp-content/plugins/wordpress-https/lib/WordPressHTTPS/Module/Core.php on line 429

Quotulatiousness

October 19, 2012

F-35 delays mean extended life for the F-16

Filed under: Military, Technology, USA — Tags: , , , — Nicholas @ 08:14

Strategy Page looks at the F-16, the “cheap and cheerful” alternative for many countries who are watching and waiting as the F-35 program staggers on.

Many air forces are finding that it’s more cost-effective to upgrade via new electronics and missiles and, as needed, refurbishing engines and airframes on elderly existing fighters, rather than buying new aircraft. This is especially the case if the new electronics enable the use of smart bombs. One of the more frequently upgraded older fighters is the American F-16. Even the U.S. Air Force, the first and still largest user of F-16s is doing this with some of its F-16s.

The U.S. Air Force is currently refurbishing several hundred of its 22 ton F-16 fighters, because their replacement, the 31 ton F-35 is not arriving in time. This is the same reason for many nations to upgrade their F-16s. Some of these nations are holding off on ordering F-35s (or cancelling existing orders), either because of the high price or doubts about how good it will be. Aircraft manufacturing and maintenance companies see a huge market for such upgrades. Half or more of the 3,000 F-16s currently in service could be refurbished and upgraded to one degree or another. That’s over $25 billion in business over the next decade or so.

The F-35 began development in the 1990s and was supposed to enter service in 2011. That has since slipped to 2017, or the end of the decade, depending on who you believe. Whichever date proves accurate, many F-16 users have a problem. Their F-16s are old, and by 2016 many will be too old to operate. Some other nations have even older F-16s in service.

[. . .]

Although the F-35 is designed to replace the F-16, many current users will probably keep their F-16s in service for a decade or more. The F-16 gets the job done, reliably and inexpensively. Why pay more for new F-35s if your potential enemies can be deterred with F-16s. This becomes even more likely as the F-35 is delayed again and again. Finally, the upgrade is a lot cheaper, costing less than $20 million, compared to over $100 million for a new F-35. If your potential enemies aren’t upgrading to something like that, a refurbed F-16 will do.

July 9, 2012

The F-35 is “unaffordable and simply unacceptable”

Filed under: Military, Technology, USA — Tags: , , , , — Nicholas @ 12:46

Winslow Wheeler on the near-doubling of the F-35 price (so far):

On June 14 — Flag Day, of all days — the Government Accountability Office released a new oversight report on the F-35: Joint Strike Fighter: DOD Actions Needed to Further Enhance Restructuring and Address Affordability Risks. As usual, it contained some important information on growing costs and other problems. Also as usual, the press covered the new report, albeit a bit sparsely.

Fresh bad news on the F-35 has apparently become so routine that the fundamental problems in the program are plowed right over. One gets the impression, especially from GAO’s own title to its report, that we should expect the bad news, make some minor adjustments, and then move on. But a deeper dive into the report offers more profound, and disturbing, bottom line.

Notorious for burying its more important findings in the body of a report — I know; I worked there for nearly a decade — GAO understates its own results on acquisition cost growth in its one-page summary, which — sadly — is probably what most read to get what they think is the bottom line.

[. . .]

Set in 2001, the total acquisition cost of the F-35 was to be $233.0 billion. Compare that to the current estimate of $395.7 billion: cost growth has been $162.7 billion, or 70%: a lot more than what GAO stated in its summary.

However, the original $233 billion was supposed to buy 2,866 aircraft, not the 2,457 currently planned: making it $162 billion, or 70%, more for 409, or 14%, fewer aircraft. Adjusting for the shrinkage in the fleet, I calculate the cost growth for a fleet of 2,457 aircraft to be $190.8 billion, or 93%.

The cost of the program has almost doubled over the original baseline; it is not an increase of 42%.

May 10, 2012

British aircraft carriers to be equipped with F-35B in policy reversal

Filed under: Britain, Military — Tags: , , , — Nicholas @ 10:30

The two Queen Elizabeth class aircraft carriers being built for the Royal Navy were originally to be equipped with F-35B model which can operate in VTOL mode (like the Harriers used on HMS Ark Royal up to her retirement). This was deemed to be too expensive, so the British government ordered the carriers to be retro-fitted with catapults and conventional landing equipment so the RN could use the (relatively) cheaper F-35C.

The plan has now been revised back to the original:

The Ministry of Defence is to abandon plans to buy the preferred fighter for the Royal Navy’s new aircraft carriers, in an embarrassing U-turn for David Cameron.

The prime minister personally endorsed the decision to equip the over-budget carriers with “cats and traps” so they could catapult and recover a version of the F-35 joint strike fighter (JSF) from their decks.

But the cost of converting the carriers has already reached £2bn, and the JSF model Downing Street wanted has been beset by delays and technical problems.

The aircraft will now not be ready until 2023 at the earliest, forcing the government to revert to Labour’s original plans to buy the less capable jump jet model.

Philip Hammond, the defence secretary, is due to make an announcement in the Commons on Thursday explaining the about-face, which was approved by the National Security Council on Tuesday.

It should be no surprise at all that Lewis Page is ready to call this decision idiotic (and he’s almost certainly right):

It’s well known that the F-35B will cost a lot more to buy and more to run than the F-35C catapult version: and it’s also well known that the main cost of aircraft carriers is not the ships but the planes. So, right out of the gate, we can see that this is a foolish decision.

In fact it’s a lot worse than it seems, as the contest in real life was not between the F-35B and the F-35C: it was between the F-35B and — for the immediate future — one or another cheap, powerful, modern carrier jet already in service. This would most most likely have been the F-18 Hornet as used by the US Navy and many other air forces around the globe, but possibly the French Rafale instead of or alongside Hornets.

In fact the UK will not be able to afford either the F-35B or the F-35C in any large numbers any time soon. Both planes are, after all, brand new supersonic stealth aircraft — only the second make of supersonic stealth aircraft ever built, in fact, and the first ever which can land on ships. They are brand new, bleeding edge kit and will cost accordingly. Both planes are still in flight test at the moment, in fact, and the F-35 programme as a whole has suffered serious cost and time overruns. This has led to delays to US orders, which have in turn pushed up costs for other early purchasers. Production is still at a low rate only.

Thus, if the Royal Navy had managed to get its hands on a catapult carrier, it would have been compelled (very happily!) to buy or lease an interim carrier jet to tide it over until a reasonable number of F-35Cs could be bought for a reasonable price — probably at some point in the 2020s. There would be no need for a full force of F-35Cs any sooner than the 2030s, by which point they would be affordable and there might be a real need for their stealth and other advanced capabilities.

April 30, 2012

The F-35, the “supersonic albatross”?

Filed under: Cancon, Military, Technology — Tags: , , , — Nicholas @ 12:24

Foreign Policy has a feature up called “The Jet That Ate the Pentagon” by Winslow Wheeler:

The United States is making a gigantic investment in the F-35 Joint Strike Fighter, billed by its advocates as the next — by their count the fifth — generation of air-to-air and air-to-ground combat aircraft. Claimed to be near invisible to radar and able to dominate any future battlefield, the F-35 will replace most of the air-combat aircraft in the inventories of the U.S. Air Force, Navy, Marine Corps, and at least nine foreign allies, and it will be in those inventories for the next 55 years. It’s no secret, however, that the program — the most expensive in American history — is a calamity.

[. . .]

How bad is it? A review of the F-35’s cost, schedule, and performance — three essential measures of any Pentagon program — shows the problems are fundamental and still growing.

First, with regard to cost — a particularly important factor in what politicians keep saying is an austere defense budget environment — the F-35 is simply unaffordable. Although the plane was originally billed as a low-cost solution, major cost increases have plagued the program throughout the last decade. Last year, Pentagon leadership told Congress the acquisition price had increased another 16 percent, from $328.3 billion to $379.4 billion for the 2,457 aircraft to be bought. Not to worry, however — they pledged to finally reverse the growth.

The result? This February, the price increased another 4 percent to $395.7 billion and then even further in April. Don’t expect the cost overruns to end there: The test program is only 20 percent complete, the Government Accountability Office has reported, and the toughest tests are yet to come. Overall, the program’s cost has grown 75 percent from its original 2001 estimate of $226.5 billion — and that was for a larger buy of 2,866 aircraft.

At those prices, there are few allies who will be able to afford them — Canada clearly not among them.

April 20, 2012

Confused about the F-35 program? Scott Feschuk will help you

Filed under: Cancon, Government, Humour, Military — Tags: , , , , — Nicholas @ 12:51

No, really:

What exactly is an F-35?

It’s a new fighter jet being manufactured by Lockheed Martin. Its full name is the Joint Strike Fighter F-35 Lightning II. We probably shouldn’t be at all concerned that this sounds like something a little boy would name his tricycle.

What’s this got to do with Canada?

All the cool countries are getting F-35s, so we’re buying some too. In fact, our Department of National Defence wanted this hip new toy so badly that it structured the procurement process to ensure no other jet could win. In 2010, the Conservative government dutifully announced plans to purchase 65 F-35 fighters, at a cost of $9 billion. On one hand, that sounds like a lot of money, but on the other hand, why do you hate our troops, first hand?

[. . .]

Doesn’t $9 billion seem like a reasonable price for basically a whole new air force?

Did the government say $9 billion? It meant $15 billion, by which it actually meant $25 billion.

Wait — why have the numbers changed?

That meddling Auditor General of ours happened to notice that National Defence low-balled the total cost of the F-35 program by the teeny-tiny amount of ten thousand million dollars.

Defence Minister Peter MacKay said this was “a matter of accounting.” What he meant was that he and his cabinet colleagues were “a-counting” on Canadians not catching on to the fact they were concealing some $10,000,000,000 in costs.

That’s a lot of zeroes.

I’ll thank you not to refer to members of the federal cabinet that way.

April 16, 2012

A more sensible way to analyze the F-35 issue

Filed under: Cancon, Economics, Military — Tags: , , , — Nicholas @ 09:15

In the National Post, Shaun Francis and John Kelleher offer an easier-to-understand method of analyzing the costs and benefits of the F-35 program:

Consider a car. Let’s say you’re considering buying a subcompact or an SUV, which you plan to hold onto for five years. A subcompact has a one-time purchase cost of $20,000 followed by $7,000 in annual, recurring costs on things like gas and maintenance. Your total costs over five years are therefore $55,000, or $11,000 average cost/year.

Meanwhile, the SUV has a one-time purchase cost of $25,000 and recurring costs of $7,500, leading to a five-year total cost of $62,500, or $12,500 average total cost/year.

To examine whether buying an SUV makes sense, you take the costs of the SUV and you subtract the costs of your next best alternative, the subcompact. Then you ask yourself, is it worth a premium of $1,500 per year to drive an SUV versus a subcompact?

From a decision point of view, it doesn’t make sense to get upset over the $62,500 total cost of the SUV. That’s not the pertinent figure here. You can’t walk to work. You need a car. So the pertinent question is the cost differential — in this example the $7,500 premium between your preferred choice and the next best option.

Canada’s F-35 decision should have been framed in a similar fashion by the Auditor General. The appropriate question? Do we want to pay a premium for the world’s best fighter jet, which will be cutting edge for decades to come, or can we make do with more reasonably priced planes that are bound to become obsolete sooner?

In the article they say “no one is questioning whether Canada needs fighter jets”, which is not actually true. Significant portions of the NDP, the Greens, and even some Liberals feel we should not be buying any military equipment that does not have a primarily humanitarian use. In their view, transport aircraft might be acceptable but combat aircraft would not. Trucks, yes, but tanks, no.

April 8, 2012

The F-35 program is “Military Keynesianism”

Wayne K. Spear explains the ordinary and the extraordinary parts of a military procurement process, as illustrated by the F-35 project:

A straight-shooting bureaucrat will admit that procurement processes are often initiated with the final selection a foregone conclusion. If you know in advance what you need, and you furthermore know who’s most qualified to deliver, then formalities intended to promote transparency and accountability are at best inconveniences to circumnavigate — and every public servant knows well how to steer that ship. That this occurs regularly within the bureaucracy is an open secret.

The Joint Strike Force program, at the centre of which is a proposed purchase of F-35 fighters, introduces disturbing wrinkles to an otherwise unremarkable bureaucratic occurrence. On military matters I refer to the self-described “prolific Ottawa blogger” Mark Collins , who has been training his keen eye on this fiasco for years. At his site you’ll find links to a range of useful resources, for example a DND PowerPoint which makes it clear that military leaders chose the F-35 and only later manufactured the selection criteria. Again, not unusual in procurement. The department however did so on grounds no one has yet admitted, never mind defended. That’s only one of many problems.

Reviewing the Auditor General’s report and the media coverage of this issue, I infer that the F-35 achieved the status of a foregone conclusion for the following reasons. 1) Canada had invested millions of dollars into the F-35 program as early as the 1990s; 2) Lockheed Martin Aeronautics lobbied aggressively, and more effectively, than its rivals (and employed Prospectus Associates, a consultancy firm with the inner track to Defence Minister Peter MacKay); and 3) the F-35 series of fighters — although years from completion and with many important details unclear and ever-changing (including year of completion, engine cost, cost to maintain) — were the only “fifth generation” fighters on the table. As the Auditor General points out, fifth generation “is not a description of an operational requirement.” My own research suggests this phrase means something like ”Ooo!” — which is what I often say when I see a jet fighter in action.

It’s a given that the Royal Canadian Air Force needs to address the rapidly aging CF-18 fleet before 2020 (the estimated end-of-life for the current fighters). The choice had appeared to be simple: follow on our pre-existing development deal with a purchase of F-35 fighters. The problems were that the development schedule had slipped multiple times, the estimated costs had climbed and climbed again, and the technical “teething” issues were still promising longer delays and higher costs. Canada had intended to buy 65 aircraft — in my opinion at least 33% less than the RCAF actually needed — at a “fixed” cost.

The F-35 is still years away from being in service in any air force, there’s no way to be sure that the government’s budget will be enough to buy the minimum number of aircraft, and the CF-18 isn’t getting any younger.

We need (some) new fighter aircraft in the next eight years, but the F-35 is no longer the automatic choice to fill that role.

There’s another root problem, and it’s also to be found in the 2012 federal budget. This document superstitiously relies on the notion that everything the feds do creates jobs. Every spending initiative in the budget creates jobs. Every departmental trim, and every restraint, ditto. Having gone through the budget, I wonder if Mr. Flaherty thinks a job is created when he sneezes. At the same time I was reading the budget, I was reviewing the federal government’s 2010 F-35 sales pitch — which, coincidentally, was the DND’s and Lockheed Martin’s sales pitch. Again, it’s all about “industrial benefits.” Lo and behold: the F-35 program creates jobs!

One name for this line of argument is “Military Keynesianism,” the idea that a brilliant and effective way to create jobs and boost the economy is to give folks like Lockheed Martin billions of dollars of public money. In the 1980s, the American public heard many Pentagon procurement stories concerning $40 staplers and $200 hammers, all part of a federal stimulus effort which by 1988 had tripled the nation’s deficit. There are distinctions to be made between this and the present case. Nonetheless, these staplers and hammers came to my mind as I dug down into the bogus F-35 procurement process and my shovel chipped the Reagan-era bedrock.

April 4, 2012

David Akin: The F-35 fiasco is now a boondoggle

Filed under: Bureaucracy, Cancon, Government, Military — Tags: , , , , , — Nicholas @ 10:21

Nobody in the government or the Department of National Defence comes off well in this politico-techno-bureaucratic mess:

The acquisition process to replace our aging CF-18 fighter jets can now officially be proclaimed as the F-35 boondoggle.

In a damning report Tuesday, Auditor General Michael Ferguson said the whole process in which the Harper Conservatives decided to allocate at least $25 billion over the next 20 years to buy 65 F-35 Lightning II “fifth generation” fighter jets was gummed up by Department of National Defence bureaucrats — and possibly air force officers — who flat out lied to their political masters and to Parliament about the costs and risks associated with the program.

The only good news is we have not yet spent that $25 billion or signed any contracts.

Canada has generally been well served by the civil service (I grit my teeth to say that, as I’m not at all fond of big government), if only in comparison to other countries. One of the better inheritances from Britain is the (relatively) non-political, impartial bureaucracy. In this case, however, the bureaucracy has failed, and failed spectacularly:

But the politicians, like any prime minister or cabinet minister before them, has to be able to rely on the bureaucracy to give them the straight goods.

That did not happen.

Here’s Ferguson in his report: “National Defence told parliamentarians (last year) that cost data provided by U.S. authorities had been validated by U.S. experts and partner countries which was not accurate at the time. At the time of its response, National Defence knew the costs were likely to increase but did not so inform parliamentarians.”

In other words, DND bureaucrats lied. Full stop. Period.

Here’s another paragraph from Ferguson: “Briefing materials did not inform senior decision-makers, central agencies, and the Minister [of National Defence] of the problems and associated risks of relying on the F-35 to replace the CF-18.”

And another: “We found that the ministers of National Defence and Industry Canada and those ministers on the Treasury Board were not fully informed (in 2006) about the procurement implications.”

I’ve been less-than-fully-supportive of the F-35 acquisition, as a quick perusal of F-35 related posts will show, but this is now much more important than the question of what aircraft (if any) the RCAF will be purchasing. It’s now a case of finding out how deep the rot is in the DND and whether the RCAF actively aided the deception. If so, heads must roll.

Update: MILNEWS.ca has a round-up of reporting on the Auditor General’s report, focusing on the F-35 program.

March 29, 2012

F-35 and the “bubbling skin” problem

Filed under: Cancon, Military, Technology — Tags: , , , — Nicholas @ 11:25

Michael Byers and Stewart Webb report on the latest technical glitch to be reported in the F-35 development:

The ability of F-35s to avoid radar detection depends on a “fibre mat,” which is cured into the composite surfaces of the aircraft.

In December 2011, a test version of the F-35 for the first time achieved the design speed of Mach 1.6. According to Bill Sweetman of Aviation Week, the flight caused “peeling and bubbling” of the stealth coating on the horizontal tails and damage to the engine’s thermal panels, and the entire test fleet was subsequently limited to Mach 1.0.

Repairing and replacing stealth materials is a time- and technology-intensive process that reduces the “mission capable rate” of aircraft. Indeed, it has been reported by the U.S. Congressional Research Service that after five years of service the F-35’s sister plane, the F-22, has a mission capable rate of just 60%.

And then they touch on the issue that has been lurking below the surface for a while, regarding the small number of aircraft the RCAF will be able to afford (assuming the government goes through with the F-35 purchase):

If the F-35 has a similar mission capable rate, Canada will, at any given time, only be able to deploy approximately 44 of its planned 65 planes. When attrition through accidents is factored in — and Canada has lost 18 of its CF-18s since 1982 — we could soon have an available fleet of just 30-35 planes, or roughly half of what the Department of National Defence says we need.

That might be the crucial point on which the F-35 acquisition fails: no matter how good the aircraft are (and I believe they will eventually work through and fix all the major issues), we can’t afford enough of them. Even without taking on new missions, we need a certain minimum number of aircraft, and I thought 65 was low-balling that number. The alternatives are to buy some F-35’s and a larger number of less expensive planes like the Super Hornet, or skip the F-35 altogether and just buy a different aircraft. The problem with splitting the order is that what we’d save on reduced F-35 acquisition costs, we’d more than lose because the RCAF would have to maintain duplicate maintenance and training programs. Unlike the RAF or the USAF, the RCAF isn’t big enough to fly multiple models on an ongoing basis (and you know that the government can’t and won’t fund a larger air force budget).

March 26, 2012

Rick Mercer updates us on the status of the F-35

Filed under: Cancon, Humour, Military, Technology — Tags: , , , — Nicholas @ 06:27

March 22, 2012

GAO latest to attempt to shoot down the F-35

Filed under: Australia, Cancon, Japan, Military, Technology — Tags: , , , — Nicholas @ 12:08

The situation is looking grimmer for all potential purchasers of the F-35, not just the RCAF:

The F-35 Joint Strike Fighter, the supposed backbone of the Pentagon’s future air arsenal, could need additional years of work and billions of dollars in unplanned fixes, the Air Force and the Government Accountability Office revealed on Tuesday. Congressional testimony by Air Force and Navy leaders, plus a new report by the GAO, heaped bad news on a program that was already almost a decade late, hundreds of billions of dollars over its original budget and vexed by mismanagement, safety woes and rigged test results.

At an estimated $1 trillion to develop, purchase and support through 2050, the Lockheed Martin-built F-35 was already the most expensive conventional weapons program ever even before Tuesday’s bulletins. The Air Force, Navy and Marine Corps are counting on buying as many as 2,500 F-35s to replace almost every tactical jet in their current inventories. More than a dozen foreign countries are lined up to acquire the stealthy, single-engine fighter, as well.

[. . .]

If cuts do occur, the U.S. will be in good company. Australia, Canada and Japan have already begun backing away from the troubled JSF as the new plane has gradually exceeded their budgets. For these countries, alternatives include the Super Hornet and an upgraded F-15 from Boeing, Lockheed’s new F-16V and the European Typhoon, Rafale and Gripen fighters. But so far the U.S. military prefers the F-35, even if the stealthy jet is more than a decade late, twice as expensive as originally projected and available in fewer numbers. “We will remain committed to the long-term success of the F-35 program,” Air Combat Command asserted.

Update, 23 March: The summary of the GAO report with a link to the PDF version for download.

March 13, 2012

Yet another straw in the wind on Canada’s F-35 plans

Filed under: Cancon, Government, Military, Technology — Tags: , , , — Nicholas @ 14:56

An article by Murray Brewster, published in the Winnipeg Free Press looks at more signs that Canada may not be as tightly bound to their F-35 purchase plans:

The point man on the F-35 stealth fighter purchase says the Conservative government has not ruled out abandoning the troubled project.

“We have not, as yet, discounted the possibility, of course, of backing out of any of the program,” Julian Fantino associate defence minister, told the Commons defence committee on Tuesday.

He made the comment after a series of pointed questions from both opposition parties.

Fantino said the government is still committed to buying the radar-evading jet, but no contract has been signed.

The Conservatives still believe the high-tech jet is the best choice to replace the aging CF-18s, but the minister suggested they are taking a cautious approach.

None of the other nine allied nations involved in the program has yet withdrawn and the minister said: “We are not.”

[. . .]

In months of questioning in the House of Commons, Fantino has insisted there is no need for a backup plan in case of further delays in the project as the manufacturer works out software and design glitches.

But on Tuesday, he told the committee he was waiting for defence officials to prepare alternate scenarios to the F-35 deal, the so-called Plan B that opposition parties have demanded.

February 23, 2012

Canada considers delaying F-35 aircraft order

Filed under: Cancon, Military, Technology — Tags: , , , , — Nicholas @ 11:38

In the Globe & Mail, Steven Chase on the Canadian government’s uncomfortable position on the RCAF’s next generation fighter aircraft:

The Canadian government is investigating whether it can squeeze more life out of its aging CF-18 fighters as it takes stock of decisions by cash-strapped allies to delay or trim orders for the replacement F-35 Lightning jet.

The Harper government must now decide whether there’s a benefit to postponing part of Canada’s order of 65 jets so that its Lightning fighter bombers are built in the same years as the bulk of orders placed by other countries — when the production cost is lower.

[. . .]

The Canadian government had planned to start taking delivery of new F-35 fighter bombers in 2016 or 2017 and has publicly described 2020 as the retirement date for most of its fleet of CF-18 Hornets.

A government official with knowledge of the file said the military is now assessing whether 2020 is the absolute maximum life expectancy for the Hornets or whether there’s a little bit more flying time left in the jets — planes purchased between 1984 and 1988.

Canada has already retrofitted the CF-18s in order to make them last until 2020.

February 15, 2012

More speculation that Canada might be reconsidering the F-35 fighter purchase

Filed under: Australia, Cancon, Military, Technology — Tags: , , , , , — Nicholas @ 10:53

In the National Post, John Ivison reports on a new tender for UAVs and wonders if it may herald a reconsideration of the government’s announced F-35 purchase.

Sources said the Department of National Defence is preparing to tender a contract for around six remotely piloted vehicles such as the MQ-9 Reaper, which the U.S. Defence Department estimates cost around $30-million each. A spokesman for DND dismissed the suggestion that armed drones could replace the F-35s, or augment a reduced number of aircraft, as speculation.

The Canadian military has previously leased drones from Israel and the CU-170 Herons flew reconnaissance missions in Afghanistan. But the Herons were never armed and a move to fit munitions on to any unmanned aircraft would inevitably draw criticism from opposition parties. When the idea was raised two years ago, then New Democrat defence critic Jack Harris dismissed it as “morally repugnant” and “robot warfare.”

In 2009, it was mentioned that Canada had been using Heron UAVs for about a year (long enough that Australian troops were in Canada to train on the equipment at that time). Of course, you can’t (currently or in the near future) completely replace manned fighters with UAVs, but UAV capabilities have grown substantially and they can now accomplish many missions that used to require manned aircraft. (See the comments on this article for some useful discussion on that topic.)

The F-35 should be (once all the development and manufacturing issues have been worked out) a very impressive combat aircraft. Here’s a graphic showing the kind of armament the F-35 will be able to use. The problem for Canada and other countries intending to purchase the F-35 is that costs are rising uncomfortably fast:

However, delays and cost overruns to Lockheed Martin’s F-35 strike fighter jet are causing headaches in many NATO capitals. Peter MacKay, the Defence Minister, admitted Tuesday that “the program has not been without problems in timelines and cost estimates.”

He said the government remains committed to giving the air force “the best opportunity for mission success” but refused to confirm that the government still intends to buy 65 F-35s.

In Question Period, the Prime Minister said that there is a budget for the F35s and “the government will operate within that budget.”

The problem for the Tories is that the cost of the planes is likely to rise considerably from the estimated $75-million per plane. Buying 65 jets would burst the $9-billion budget allocated for the F-35 purchase.

The U.S. Defence Department estimates the cost of each F-35 at $195-million this year. The Pentagon said Monday it intends to reduce spending on the F-35s next year and delay future spending because of the soaring costs and technological problems.

Some countries are opting to buy some F/A-18F Super Hornets as a stopgap until the F-35 is mature (Australia, for example, ordered 24 aircraft at a reported cost of A$6.6 billion).

No story about military equipment purchases is complete without considering the fact that the government thinks of it as an economic development program nearly as much as a military purchase. In spite of the remarkably poor economic justification, it has political benefits that easily dazzle parliamentarians and local newspaper editors (in the regions that benefit from the spending, anyway).

The Harper government has argued consistently one reason to stay in the F-35 program is the industrial benefits that have accrued to some Canadian companies. However, one industry insider said more work would likely flow from an order for a less expensive jet from Boeing or Saab. The government is set to unveil a comprehensive review of the Canadian aerospace industry, led by former Industry Minister David Emerson. If his review were to encompass the F-35 purchase, it could provide the Tories with the perfect cover to cancel a program that is turning into a political millstone.

Also in the National Post, Matt Gurney points out that it’s not just the NATO allies getting concerned about the F-35 program:

Ottawa is said to be considering equipping the Air Force with armed drones as part of an effort to replace the aging CF-18 fighter jets. The original plan was to replace them with 65 F-35s, but that problem has been beset by cost overruns and production delays. While the Harper government has remained resolutely behind the F-35 purchase, news has emerged out of Washington that the United States is beginning to cancel or delay orders for the advanced stealth fighter jets. This is a game-changer — it’s one thing for Italy or Israel to get cold feet, but if America pulls the plug on the program, the entire calculus of the F-35′s economics could change rapidly. And not in Canada’s favour.

He also points out that it’s no longer safe to assume that your UAV will perform as expected once your opponent reaches a certain level of technical sophistication:

Last December, Iran announced that it had shot down a U.S. RQ-170 drone over its territory. There was nothing new about that, and nor was it particularly alarming — an advantage of using drones for reconnaissance is that if the enemy does blow one up, you don’t necessarily need to respond with a retaliatory strike, as would be far more likely if a pilot (with a family and an elected representative and a Facebook page) was killed or captured. It also helps avoid a repetition of the awkward Gary Francis Powers incident of the Cold War, where an American spyplane pilot was shot down over the Soviet Union. When America denied the flight had ever occurred, the Soviets displayed a very much alive Powers to the media, humiliating the United States. Having a drone blown out of the sky isn’t nearly as complex. You just build another drone.

After several days, however, it became clear that there was more to the story than we had first been led to believe. Iran hadn’t shot down the drone at all. It had done something much worse — it had hacked the drone, and seized control of it. Iranian ground controllers, having assumed command of the drone, were able to successfully land it in their territory as a prize. Now, one of the most advanced pieces of spy technology in the United States’ military inventory, loaded with all sorts of high-tech monitoring and communications gear, is being reverse-engineered by a hostile regime. Worse: You can be certain that Iran will have no qualms about sharing access with whatever it learns, or perhaps even the drone itself, with Chinese and Russian engineers. Just a small way of saying thanks for all the missiles and UN vetoes Iran’s friends have provided over the years. (Early consideration of sending in U.S. commandos to blow up the drone, or destroying it from afar with an airstrike, were rejected for fear of triggering an all-out war and because U.S. officials hoped that Iran wouldn’t know what to do with the technology — but the Russians and Chinese will likely have no such problems.)

Update: Kelly McParland on the luck of Stephen Harper:

Stephen Harper is one lucky politician.

Here he is, stuck with a bad decision to buy a bunch of fighter planes the country can’t afford and might not need, a decision he has defended so many times there is now no way out save through an admission of error and embarrassing public climbdown. Which, knowing our Prime Minister, we can safely predict would happen just about the time the last polar ice cap melts away.

Then along comes a solution with his name on it, all wrapped up in pretty ribbon and accompanied by a “get out of embarrassment free” pass. Once again you can picture Bob Rae lying awake in bed at night, cursing softly and muttering “How does the *!@*%$-ing son-of-a-#%&% do it?”

Mr. Harper’s gift, which arrived, appropriately enough, on St. Valentines Day, comes in the form of further evidence that other would-be buyers of the F-35 fighter jet are heading for the exits. Italy chopped its order by 30% this week, Britain says it won’t make up its mind until 2015, Turkey has reduced its order by 50% and Australia is having doubts. On Monday the Pentagon said it’s delaying its own purchase of 179 of the planes by five years to save $15 billion and allow yet more time for testing. Let’s repeat that: The U.S., which is building the plane and marketing it like crazy to any ally that will listen, says the plane isn’t ready yet and it can’t afford the thing itself.

February 11, 2012

Canada calls for a meeting of other countries buying the F-35 fighter

Filed under: Cancon, Military, Technology — Tags: , , — Nicholas @ 12:25

Just when you think the Canadian government is going to keep kicking the F-35 can down the road, meekly accepting the repeated delays, they suddenly make headlines:

Washington’s plan to further slow production of the F-35 Joint Strike Fighter is prompting Canada to convene a meeting with seven other international partners as the countries rethink their own orders for the stealthy new fighter jet.

Canada has committed to purchasing as many as 65 of the planes, but delays and shrinking orders threaten to drive up costs each country must bear for what is already the most expensive weapon system in history.

The Pentagon is restructuring the program for the third time in recent years; a move that will delay savings that would come from building more planes faster.

While I strongly doubt the Canadian government will pull out of the F-35 program — it’s been a key part of the Conservative defence plan — it’s a bit of a change to see them making waves about the delays and cost increases. Even if they eventually get some sort of a break on the final pricing, 65 aircraft are going to be too few to meet current needs but there’s little chance of the government increasing the funding to buy more.

Lockheed Martin Corp., the Pentagon’s No. 1 supplier, and U.S. officials who run the $382-billion US weapons program are anxiously preparing for a meeting in Australia in mid-March where the partners — Canada, Britain, Denmark, Norway, Italy, Australia, Turkey and the Netherlands — will outline their revamped procurement plans.

But Canada has tentatively scheduled a meeting of the partners at its embassy in Washington before the Australian meeting to get an update on the program and better coordinate their approach.

Each U.S. restructuring has consequences for the partners, which have already chipped in hundreds of millions of dollars for development of the fighter, which was sold as an affordable way to replace a dozen older jets in use around the world.

Canada’s plan to purchase up to 65 of the jets is based on a very specific timetable, and a slower ramp-up in production could force a tough decision between paying more per plane or extending the life of the country’s CF-18s. The government has estimated the jets would cost $16 billion, including maintenance. Others have pegged the cost at up to $30 billion.

« Newer PostsOlder Posts »